Large-Load (Data Center) Electric Cost-Allocation Tariffs: 50-State Survey
State-by-State Detail
PENDING
- PG&E's Electric Rule 30 uniform transmission-interconnection tariff (A.24-11-007) has only interim approval requiring up-front payment; the final decision and refund cost-allocation remain pending.[1]
- SB 886 would require a dedicated data-center tariff at 25 MW, with full cost responsibility for interconnection upgrades, a 15-year zero-carbon energy contract, and an exit fee.[2]
- An April 2026 CPUC rate-design rulemaking (implementing SB 57) is examining dedicated tariffs and demand charges for data centers; SB 57 itself directs only a study, due Jan. 1, 2027.[3]
- Separately, the Imperial Irrigation District (public power) has a Large Load Tariff Schedule.[4]
- Next expected action: CPUC final decision on PG&E Electric Rule 30 (A.24-11-007, now interim); SB 57 data-center rate-design study due January 1, 2027; SB 886 pending in the Legislature.[5]
Sources
[1] ('CPUC Weighs Cost Recovery for Interconnection...', by Seth Hilton, Lilly McKenna, Sam Wong, Stoel Rives LLP, Published By JD Supra; 'CPUC Weighs Cost Recovery for Interconnection...', by Seth Hilton, Lilly McKenna, Sam Wong, Stoel Rives LLP, Published By JD Supra)
[3] ('CPUC Will Address Electric Rate Impacts of Data...', by Louise Dyble, Hanson Bridgett, Published By JD Supra; 'California Governor Vetoes Proposed Data Center...', by Alexander Ames, Christopher Powell, Hanson Bridgett, Published By JD Supra)
[4] (DELTa: Database of Emerging Large Load Tariffs at 13)
[5] ('CPUC Weighs Cost Recovery for Interconnection...', by Seth Hilton, Lilly McKenna, Sam Wong, Stoel Rives LLP, Published By JD Supra; 'California Governor Vetoes Proposed Data Center...', by Alexander Ames, Christopher Powell, Hanson Bridgett, Published By JD Supra)
APPROVED + PENDING
- Approved (1): Black Hills Colorado Electric's Economic Development Rate (Proceeding 25A-0500E, C26-0229, April 2026, affirmed C26-0345) — a 10% discount floored at marginal cost, 60 MW cap, with an express commitment that retail customers are not assigned transmission/distribution interconnection or construction costs.[1]
- Approved (2): Public Service Company's customer-specific QTS Aurora data-center contract (Proceeding 23A-0330E, 2024) — QTS pays 100% of customer-funded transmission (~$28.1M), $1.06M security, 10-year term with clawback.[2]
- Pending: Public Service's Schedule TL / Large Load Tariff (Docket 26AL-0137E) was suspended and set for en banc hearing by Decision C26-0280 (April 30, 2026) — not approved. It applies to load 50 MW or more, socializes network-transmission reinforcements across the Schedule TL class while direct-assigning customer-specific interconnection facilities, with an 80% minimum bill and 15-year term.[3]
- Other: two 2026 bills (SB26-102, HB26-1030) failed, and Tri-State's wholesale High Impact Load Tariff was rejected by FERC.[4]
- Next expected action: En banc hearing on Public Service's Schedule TL (Docket 26AL-0137E), set by Decision C26-0280 (April 30, 2026); the tariff is suspended pending that hearing, the date of which is not stated in the located sources.[5]
Sources
[1] (In the Matter of the Application of Black Hills Colorado Elec., LLC, for Approval of Its Econ. Dev. Tariff (Edr)., No. 25A-0500E, 2026 WL 1603172 (May 27, 2026); In the Matter of the Application of Black Hills Colorado Elec., LLC, for Approval of Its Econ. Dev. Tariff (Edr)., No. 25A-0500E, 2026 WL 1031938 (Apr. 13, 2026); In the Matter of the Application of Black Hills Colorado Elec., LLC, for Approval of Its Econ. Dev. Tariff (Edr)., No. 25A-0500E, 2026 WL 1031938 (Apr. 13, 2026))
[2] (IN THE MATTER OF APPLICATION OF PUBLIC SERVICE COMPANY OF COLORADO FOR APPROVAL OF A NON-STANDARD EDR CONTRACT, AND FOR DETERMINATION NO CPCN IS NEEDED FOR CUSTOMER-FUNDED TRANSMISSION FACILITIES., No. R24-0168, 23A-0330E, 2024 WL 1236962; IN THE MATTER OF APPLICATION OF PUBLIC SERVICE COMPANY OF COLORADO FOR APPROVAL OF A NON-STANDARD EDR CONTRACT, AND FOR DETERMINATION NO CPCN IS NEEDED FOR CUSTOMER-FUNDED TRANSMISSION FACILITIES., No. R24-0168, 23A-0330E, 2024 WL 1236962; IN THE MATTER OF APPLICATION OF PUBLIC SERVICE COMPANY OF COLORADO FOR APPROVAL OF A NON-STANDARD EDR CONTRACT, AND FOR DETERMINATION NO CPCN IS NEEDED FOR CUSTOMER-FUNDED TRANSMISSION FACILITIES., No. R24-0168, 23A-0330E, 2024 WL 1236962)
[3] (IN THE MATTER OF ADVICE LETTER NO. 2018 - ELECTRIC FILED BY PUBLIC SERVICE COMPANY OF COLORADO TO REVISE COLORADO P.U.C. NO. 8 - ELECTRIC TARIFF TO ADDRESS LARGE LOADS, ADD A NEW SCHEDULE TRANSMISSION LARGE SERVICE (SCHEDULE TL) RATE, ADD A NEW CLEAN TRANSITION TARIFF (SCHEDULE CTT), AND IMPLEMENT CHANGES TO THE TRANSMISSION LINE EXTENSION POLICY, TO BECOME EFFECTIVE MAY 3, 2026., No. 26AL-0137E, C26-0280, 2026 WL 1282969; IN THE MATTER OF ADVICE LETTER NO. 2018 - ELECTRIC FILED BY PUBLIC SERVICE COMPANY OF COLORADO TO REVISE COLORADO P.U.C. NO. 8 - ELECTRIC TARIFF TO ADDRESS LARGE LOADS, ADD A NEW SCHEDULE TRANSMISSION LARGE SERVICE (SCHEDULE TL) RATE, ADD A NEW CLEAN TRANSITION TARIFF (SCHEDULE CTT), AND IMPLEMENT CHANGES TO THE TRANSMISSION LINE EXTENSION POLICY, TO BECOME EFFECTIVE MAY 3, 2026., No. 26AL-0137E, C26-0280, 2026 WL 1282969)
[4] (Tri-State Generation & Transmission Ass'n, Inc., 193 FERC ¶ 61,070, 2025 WL 3127637 (2025))
APPROVED + PENDING
- Approved: the Florida PSC approved Large Load Contract Service tariffs (Final Order PSC-02026-0022-S-EI, Jan. 22, 2026), and SB 484 (eff. July 1, 2026) defines a "large load customer" at 50 MW and requires each to bear its full cost of service.[1]
- Pending: Duke Energy Florida's proposed Large Load Customer class and LLC-1 rate schedule (Large Load Policy at 100 MW, with minimum term, minimum bill, security, early-termination, system-impact fee, and CIAC up to 100%) was suspended pending review in Docket 20250113-EI (Oct. 14, 2025).[2]
- Next expected action: Florida PSC review of Duke Energy Florida's suspended LLC-1 schedule (Docket 20250113-EI); SB 484 took effect July 1, 2026. No hearing date for the Duke schedule is stated in the located sources.[3]
Sources
[1] ('Florida Senate Bill 484: Revisions To Regulations...', by Kenneth Tinkler, Carlton Fields, Published By JD Supra; 'Proposed Florida Legislation Creates New Regulatory...', by D. Bruce May, Blaine Remmick, Holland & Knight LLP, Published By JD Supra)
[3] (In Re: Petition for A Ltd. Proceeding to Approve Large Load Tariff, by Duke Energy Fla., LLC., No. 20250113-EI, 2025 WL 2948054 (Oct. 14, 2025); 'Proposed Florida Legislation Creates New Regulatory...', by D. Bruce May, Blaine Remmick, Holland & Knight LLP, Published By JD Supra)
Greenberg Traurig’s Digital Infrastructure Industry Group is dedicated to serving clients in the data center, digital infrastructure, and telecommunications industries. We understand the unique operational and legal challenges in this space and are well-equipped to help you pursue your objectives. Our team has experience advising clients on a wide range of transactions in this sector, including hyperscale leasing, land acquisitions, data center developments, joint ventures, debt financings, and mergers and acquisitions, to name a few.
National Pattern at a Glance
|
Status |
States |
|
Approved (33) — most also with pending items |
Alabama, Arkansas, Colorado, Florida, Georgia, Idaho, Illinois, Indiana, Kansas, Kentucky, Louisiana, Michigan, Minnesota, Mississippi, Missouri, Nebraska, Nevada, New Jersey, New Mexico, North Dakota, Ohio, Oregon, Pennsylvania, South Carolina, South Dakota, Tennessee, Texas, Utah, Virginia, Washington, West Virginia, Wisconsin, Wyoming |
|
Pending only (9) |
Arizona, California, Delaware, Maryland, Montana, New York, North Carolina, Oklahoma, Vermont |
|
Failed / stated intent (2) |
Alaska, Maine |
|
No action identified (6) |
Connecticut, Hawaii, Iowa, Massachusetts, New Hampshire, Rhode Island |